Improvements to your home

As well as providing a day-to-day repairs service each year we carry out a number of major repairs to homes such as fitting new kitchens or new roofs.

Together these works make up our investment programme which when complete will ensure all our homes meet the Decent Homes standard.

Please click on the link on the right to access the current West North West Homes Leeds Capital Programme.

Capital Improvement Works - Amount Spent to Date
The budget for Capital Improvement Works for the financial year 2009/10 is £24.6 million. At the end of February 2010, £14.4 million had been spent on improvement works to including work to bring properties up to the Decent Homes standard.

The following schemes started in the current month:

Demolition Work Clydes and Holdforths
The demolition of 36 properties on the Holdforths and Clydes. 
Planned to complete end of March 2010. 

The following schemes completed in the current month:

Whole House Refurbishment to block 34-44 Clyde Walk.
Queenswood Court & Heights External Work.

A brief update update on schemes that have already started:

Blenheim Square Georgian Block WHI
Scheme progressing well due to complete end of March 2010

5Ms Woodbridges External Enveloping
Scheme progressing well and due to complete early May 2010.  Delays due to poor weather conditions.

Kirkstall Miscellaneous Properties Phase 4
Re-roofing still to complete on properties next to the railway lane

New Wortley Gas Mains and New Central Heating (Heatlease)The gas mains have been installed and work has started on installing central heating.  Up to date 111 properties are having heating installed.

Rossefields and Snowdens, Bramley  Gas Mains and Central Heating (Heatlease)
The gas mains have been installed and work has started on installing central heating.  Up to date 25 properties are having heating installed.

Re-roofing ALMO Wide 09/10/11
Scheme started in January 2010, re-roofing of properties across the ALMO to meet the Decent Homes Standard.  Up to date 19 properties have been re-roofed.  Scheme planned to complete March 2011.

Replacement Kitchens and Bathrooms Phase 1
Work progressing well.  Up to date work has been completed at 46 properties (a total of 124 properties in the scheme).  Scheme planned to complete end of March 2010.